Thursday, November 21, 2013

Renovation Day 97-102


The drainage project at the bottom of 18 fairway was completed last Friday.  A flowable grout was pushed through the old 24" clay tile to stop the subsidence holes.  We tried to dig a section of the old pipe up to see the depth and the clay tiles were 12' deep at the top of the pipe in areas.  We finished sodding the practice bunker at the driving range yesterday.  It was still too wet to install the drainage.  We will have that project complete shortly.  The front 9 cart paths were finished on Friday also.  We began removing the sod and back filling next to the cart paths with soil to level the edges.  