This morning we removed the dew from the green surfaces with a filled hose.  The spray hawk was calibrated for greens and we began spaying.  Fungicide and foliar fertilizers were applied to help continue growth as much as possible.  The greens are filling in very well.  We seeded greens starting September 16th through October 1st once LaBar and Kye were finished with construction.  We have mowed all of the greens multiple times and we are already down to a mowing height of .200", just under 1/4".  Normal mowing height is .120" - .140", so we are pretty close to a playable height.  We will continue to lower the height into November to help promote lateral growth.  T&A Irrigation has completed the front 9 and have started the main line on the back and began 11 fairway today.   