Tuesday, October 29, 2013

Renovation Day 69-75




We have started the asphalt prep for the asphalt overlay for the front nine.  We rented an asphalt mill to level the current cart paths and an asphalt sweeper to remove the debris.  After the asphalt material was removed we used a cut saw to clean the joints on the asphalt to concrete connections.  The asphalt will again be removed in those areas and filled with a rock base.  The staff has also started grinding stumps and removing the chips.  We have a lot of stumps through the course and we have almost made it through the front nine already.

No comments:

Post a Comment