Sunday, August 18, 2013
Renovation Day 4
#12 green demo is underway. The irrigation around #4 green has been completed and T and A Irrigation is starting the loop around the green on #8. The new greens loops will be used to water in the newly seeded greens. They are installing full circle heads just outside the collar to water greens and part circle heads to water green surrounds. #11 and #14 herring bone drainage will be filled soon. All of the soil greens drainage needs to be completed by August 22nd. Methyl Bromide, which is a soil sterilant, will be applied to the greens on the 22nd and 23rd.